Lancashire Combined Fire Authority

Resources Committee

Meeting to be held 12 July 2023

 

Financial Monitoring 2023/24

(Appendices 1 and 2 refer)

 

Contact for further information:

Steven Brown - Director of Corporate Services – Telephone Number 01772 826804

 

Executive Summary

 

The report sets out the current budget position in respect of the 2023/24 revenue and capital budgets. The year-to-date position is broadly balanced and therefore no significant variances are forecast for the year at the time of reporting.

 

Recommendation

 

The Committee is asked to note and endorse the year-to-date position in respect of the 2023/24 revenue and capital budgets.

 

 

Information

 

Revenue Budget

Lancashire Fire and Rescue Service’s 2023/24 revenue budget has been set at £68.493m. The budget profiled to the end of May 2023 is £13.289m and expenditure for the same period is £13.243m resulting in an underspend of just (£0.045m).

 

The overall underspend position is further broken down between pay and non-pay budgets; there is an underspend of (£0.226m) on pay and an £0.181m overspend on non-pay activities. Whilst two months is a small period to determine any underlying trends it does serve as a guide for further work to identify any potential changes that may impact on the outturn position for the year. The year-to-date positions within all departmental budgets are set out in Appendix 1, with more significant variances of note shown separately in the table below: -

 

Area £’m

Overspend/ (Under spend) to 31 May 23

Reason

Fleet and technical Services -  Non-Pay

£0.086

The year to date overspend largely relates to fuel and maintenance costs, further work will be undertaken with the department to determine if there are any underlying pressures.

 

Pay

(£0.207)

Pay budgets in many areas are reporting small underspends due to vacancies however, this is not expected to continue long term. 

 

 

 

Capital Budget

 

The original Capital Programme for 2023/24 is £10.116m, a broad overview of the programme is set out below: -

 

Area

Budgeted Items

Operational Vehicles

Budget £5m

The budget allows for the remaining stage payments for 10 pumping appliances purchased in previous financial years.

In addition, the budget allows for the first stage payments of the 3 pumping appliances for the 2023/24 programme. It also includes two Climate Change Vehicles and three Command Units.

 

Other vehicles

Budget £1.0m

This budget allows for the replacement of various operational support vehicles.

 

Operational Equipment Budget £1.3m

 

This budget allows for operational equipment purchases including thermal imaging cameras and cutting and extrication equipment in 2023/24.

 

Building Modifications

Budget £1.5m

 

This budget includes the commencement of a programme of Drill Tower Replacements and an upgrade to the Wylfa prop facility.

 

IT systems

Budget £1.2m

This budget includes for upgraded Firewalls and digitisation of fire appliances.

 

 

Slippage from 2022/23 of £1.636m has been added to the original budget to give a revised budget of £11.752m. To date £1.4m has been spent predominantly on pumping appliances as set out in Appendix 2. This appendix sets out the revised capital programme and committed expenditure position against this, as reflected above.

 

Financial Implications

 

As outlined in the report

 

Business Risk Implications

 

None

 

Environmental Impact

 

None

 

Equality and Diversity Implications

 

None

 

Human Resource Implications

 

None

 

Local Government (Access to Information) Act 1985

List of background papers

Paper:

Date:

Contact:

Reason for inclusion in Part 2 if appropriate: N/a

 

 

 


APPENDIX 1

Budget Monitoring Statement at May 2023

 

 

 

 


 

APPENDIX 2

 

Capital Budget 2023/23 showing expenditure to date